Minutes of the
Environmental Management Program
Coordinating Committee
May 18, 2011
Quarterly Meeting
Holiday Inn
Rock Island, Illinois
Kevin
Foerster of the U.S. Fish and Wildlife Service called the meeting to order at 12:42
p.m. on May 18, 2011. Other EMP-CC
representatives present were Charles Barton (USACE), Mike Jawson (USGS), Rick
Mollahan (IL DNR), Pat Boddy (IA DNR), Walt Popp (MN DNR) attended on behalf of
Tim Schlagenhaft, Janet Sternburg (MO DoC), Jim Fischer (WI DNR), and Bill
Franz (US EPA). A complete list of
attendees follows these minutes.
USACE Project Development Process
Marv
Hubbell overviewed USACE’s project planning and construction process, including
the various required planning steps and levels of review. In response to requests from Rick Mollahan
and Kevin Foerster, Hubbell said he will distribute the Corps’ project
development diagram to EMP’s distribution list.
Minutes of the February 16, 2011 Meeting
Jim
Fischer moved and Rick Mollahan seconded a motion to approve the draft minutes
of the February 16, 2011 meeting as written.
The motion carried unanimously.
Program Management
FY 11 Fiscal Update
Marv Hubbell reported that the
FY 11 Full-Year Continuing Appropriation Act was enacted on April 15,
2011. USACE has recently determined
allocations to specific projects and programs from within its overall funding
under the measure, and EMP will receive $21.15 million for the year. Prior to April 15, EMP had been executing
based on a $19 million budget for FY 11, under previous continuing resolution
authorities (CRAs). However, Hubbell
said EMP is in a good position to fully execute $21.15 million. He stressed the importance for USACE programs
and projects to fully execute their allocations, explaining that falling short
will likely have implications on out-year funding. Hubbell observed that USACE’s FY 11
allocation decisions were tied very closely to the President’s original FY 11
budget request. He outlined EMP allocations
under the $21.15 million budget, as follows:
·
Regional
Administration — $868,000
·
LTRMP — $6,400,000
·
HREPs — $13,882,000
§
Program Model
Certification and Regional HREP Support — $250,000
§
MVP — $4,100,000
§
MVR — $5,432,000
§
MVS — $4,100,000
Hubbell
explained that EMP’s LTRMP priorities for FY 11 include base monitoring,
accuracy assessment of the 2010-2011 land cover/land use dataset, and systemic
LiDAR and bathymetric data collection and serving. On the HREP side of the program, EMP will
continue work on 24 habitat projects, with eight projects in construction and
16 in planning. Two new habitat projects
will also be initiated in FY 11.
In response to a question
from Janet Sternburg, Hubbell and Karen Hagerty said USACE has not yet
determined how the additional funds above the initial CRA funding level will be
spent. However, they confirmed that the
FY 10-14 LTRMP Strategic Plan will guide the additional LTRMP allocation.
FY 12 Budget Request
Hubbell
said the President’s FY 12 budget request includes $18.15 million for EMP. He reiterated the importance for USACE
programs and projects to be included in the President’s budget requests,
especially in the current federal fiscal climate.
2010 Report to Congress
Hubbell
said USACE Headquarters (HQ) is currently reviewing EMP’s 2010 Report to
Congress (RTC). Hard copies and CDs of
the report will be distributed soon.
Hubbell said Corps staff also plan to distribute a brochure summarizing
the RTC’s major highlights and recommendations this summer. In response to a question from Jim Fischer,
Hubbell said the brochure will not undergo HQ review.
EMP’s 25th Anniversary and 100,000 Acres Restored
Celebration
Hubbell
announced that Corps staff are planning a celebration of EMP’s 25th anniversary
and its restoration of 100,000 acres of aquatic habitat. The event will be held this fall. In response to a question from Kevin
Foerster, Hubbell said details concerning the event remain to be determined. However, the celebration will likely include
a site visit to an HREP. He said ASA(CW)
Jo-Ellen Darcy will be invited to attend.
EMP’s Regional Review Plan
Hubbell reported that Corps
staff are finalizing a draft EMP Regional Review Plan for MVD review. Following any revisions, MVD will transmit
the Plan to HQ for consideration.
Hubbell said the Plan identifies ways to guide and streamline HREP
reviews, in compliance with the Corps’ January 2010 project review engineering
circular (EC 1165-2-209).
Program Identification
Hubbell emphasized the
importance of identifying EMP as a program in connection with specific HREP and
LTRMP activities. Communicating EMP’s
accomplishments to its various audiences builds and maintains support for the
program. Hubbell asked that partners
send him any ideas for enhancing EMP’s visibility both generally and in the
context of specific projects and activities.
Jim
Fischer suggested that 1) public access points in LTRMP trend pools have signs
that describe EMP’s monitoring activities within that pool and 2) public
relations brochures be made available at boat landings to describe EMP’s local
monitoring and restoration efforts and provide contact information for further
inquiries. Karen Hagerty noted that EMP’s
20th anniversary brochure could be updated and used for general outreach
purposes, including distribution at boat landings. Hubbell said EMP’s 20th anniversary
postcards could also be updated and used as outreach materials. In response to a suggestion from Barry
Johnson, Hagerty said Corps staff are currently drafting language that partners
can use for crediting EMP in the program’s publications and presentations.
Increased Efficiency and Transparency of the FY 10-14
LTRMP Strategic Plan
Hubbell
explained that increased efficiency in LTRMP’s base monitoring efforts over
time is providing more opportunities for data analyses, coordination with other
research and management efforts, and HREP-LTRMP integration. Currently, priorities for how to allocate
capacity stemming from these efficiencies are determined within UMESC and
individual field stations. The work is
not being captured in LTRMP’s scopes of work (SOWs) or other reporting
mechanisms, and partners are not considering priories for this capacity as a
group. Hubbell stressed the importance
of 1) recording and communicating to stakeholders the additional work being
done under EMP, as well as partner contributions, and 2) ensuring that the
additional resources are used effectively and efficiently. He said the additional work being done should
directly support EMP’s authority and partners’ goals and objectives for LTRMP,
as articulated in the FY 10-14 LTRMP Strategic and Operational Plan. Hubbell said USACE, USGS, and the field
stations will coordinate in identifying and prioritizing these additional
opportunities.
Beginning
with FY 12 planning, Hubbell said USACE and USGS will work with field station
staff and component specialists to 1) examine the actual time required to collect
and serve the base monitoring component data and 2) establish a coordinated
process for developing and evaluating LTRMP’s annual SOWs. Hubbell encouraged partners to send him
suggestions for improving the focus and communication of LTRMP activities.
In response to a question
from Janet Sternburg, Hubbell said USACE and USGS staff typically begin
developing LTRMP’s annual SOWs in August or September prior to the fiscal year
start in October. Sternburg observed
that the relationship among LTRMP’s annual SOWs, research frameworks, and
Science Plan is unclear. Mike Jawson
said USGS staff are currently developing the research frameworks and Science
Plan, and hope to get a draft Science Plan to partners for review this
summer. Hagerty said LTRMP staff
anticipate that draft research frameworks for the aquatic vegetation and
landscape components will be completed this year.
Hubbell
said, while there is still uncertainty regarding how to develop and implement
more focused annual LTRMP SOWs, drivers for enhancing the focus of the SOWs
include 1) capturing the efficiency and effectiveness of the highly skilled
LTRMP workforce, 2) rekindling program identity, and 3) providing more
effective direction to field station, USGS, and USACE staff.
Sternburg
suggested that state managers who supervise the field station team leaders
should be invited to participate when USACE and USGS meet with each field
station. She explained that this helps
build a better understanding of EMP and the partnership within state
agencies. Bernie Schonhoff encouraged broad
participation in the next field station meeting, stressing the importance of this
opportunity to discuss LTRMP issues and priorities. Hubbell said the next field station meetings
will likely occur this fall. He noted the
value in having all partners attend the meeting to enhance program integration. Bill Franz suggested that the UMRBA Water
Quality Task Force members be invited to provide insights regarding water quality
efforts on the UMR.
Walt Popp asked Hubbell
whether the concern is with productivity or with products that do not meet
programmatic needs. Hubbell said he does
not have a blanket answer for Popp’s question.
He stressed that the width and breadth of field station activities are
not being documented and shared with partners.
As a result, there are instances of project proposals being developed in
isolation and products not being properly shared and credited. He said EMP needs to be accountable and
transparent with how it expends LTRMP funding.
Jawson added that EMP often collaborates on important research
publications, and should be credited for its contributions.
Public Involvement and Outreach
Hubbell said EMP has an
opportunity to have Tom Mangelsen, a well-known professional nature photographer,
take photographs of the UMR. EMP would
only need to pay for Mangelsen’s travel expenses on the river. Hubbell said UMESC’s new LTRMP website is up
and running, and USACE staff continue to work on revamping the HREP webpages.
Jawson
said Congressman Ron Kind (WI-D) is interested in participating in a public
event to celebrate the opening of UMESC’s new wing. Jawson said DOI Secretary Ken Salazar will be
invited to attend the event.
Implementation Issues Assessment
NGOs as Cost Share Sponsors
Marshall Plumley overviewed
WRDA 2007 and the Corps policy related to NGOs’ ability to serve as non-federal
sponsors for HREPs. He explained that
WRDA 2007 Section 2003 amended the 1970 Flood Control Act, redefining non-federal
interests to include nonprofit entities with the consent of the affected local
government. A qualifying nonprofit must
have full authority and capability to perform the terms of its agreement and to
pay damages, if necessary, in the event of failure to perform. Plumley said NGOs are subject to the same
requirements as public entities, including the following:
1. Provide the required cost share (i.e., 35 percent for
restoration), with all funds coming from non-federal sources; cost-share
extends to historic preservation mitigation
2. Provide all lands, easements, and rights-of-way,
relocation of utilities and other existing structures, and disposal of dredged
or excavated material (LERRDs)
3. Land and project many not be part of a wetland bank or
mitigation for another project
4. Operate, maintain, repair, replace, and rehabilitate
the project, or functional portion of the project, using non-federal funds,
throughout its 50-year life span
5. Maintain the federal government’s right to enter the
property
6. Hold and save the federal government free from all
damages
7. Assume all responsibility for hazardous, toxic, and
radioactive waste (HTRW) clean up and liability
8. Prevent any obstructions or encroachments to the project
9. Comply with USACE’s bookkeeping standards, the project
partnership agreement (PPA), and all applicable Federal and state laws and
regulations
Barb Naramore recalled that,
at a past EMP-CC quarterly meeting, Tim Schlagenhaft requested that the issue
paper authors consult with NGOs in developing the NGOs as Cost Share Sponsors
issue paper. In response to Naramore’s
reminder, Hubbell confirmed that the authors will consult with NGOs regarding
the project types and locations that might be of interest and their
perspectives on serving as HREP sponsors.
Meeting participants suggested that the authors consult The Nature
Conservancy, Audubon, and American Land Conservancy, as well as levee
districts.
In response to a question
from Pat Boddy, Plumley said that, if HTRW is discovered during the project’s
implementation, the NGO sponsor will need to either remove the contaminant or halt
the project.
May 19 Authors’ Forum
Hubbell said an
Implementation Issues Assessment (IIA) authors’ forum will be held on May 19,
2011. The forum will give issue paper
authors and EMP partners an opportunity to informally discuss the IIA issues
and schedule.
IIA Issue Statements
Hubbell explained that, at
its February 16, 2011 quarterly meeting, the EMP-CC adopted issue statements
for each implementation issue. However,
meeting participants also offered some modifications to certain issue
statements. Following the February 16
meeting, Hubbell said he worked with UMRBA staff to revise the issue statements
based on the meeting’s discussion.
Changes to the issue statements are shown in Track Changes on pages
A3-A9 of the meeting packet. Jim Fischer
moved and Boddy seconded a motion to approve the revisions as shown in the packet. The motion was carried unanimously.
Long Term Resource Monitoring Program
Product Highlights
Mike
Jawson reported that LTRMP has completed two manuscripts: 1) Evaluation of Single- and Two-Stage
Adaptive Sampling Designs for Estimation of Density and Abundance of Freshwater
Mussels in a
Jawson
said Nate De Jager presented at the 2011 U.S. International Association for
Landscape Ecology Symposium on 1) the effects of flood duration on vegetation
and soils on the UMR floodplain and 2) spatial clusters of total
nitrogen. He said UMESC staff continue
to work with Chinese scientists on monitoring the
Jawson
reported that UMESC has revamped the LTRMP website: http://www.umesc.usgs.gov/ltrmp.html. He asked partners to contact UMESC staff if they
encounter errors or have ideas for improving the website.
Jawson
reported that Representative Betty McCollum (MN-D) is drafting legislation that
would promote coordination on ecosystem-based management at the federal level
for the UMR. Jawson also reported that
he met with Congressional Research Service (CRS) staff who are examining major
environmental programs, including EMP.
The study is not intended as a hierarchical evaluation of the programs,
but rather is seeking to identify common elements of success. Among other things, Jawson said the CRS staff
asked his opinion of whether highly prescriptive authorizing legislation is
preferable to more flexible language.
USACE LTRMP Report
Karen Hagerty said LiDAR data in Pools 15 to 19 will
be collected this fall, contingent on favorable water levels and weather
conditions. Hagerty reported that
systemic bathymetric data have undergone
QA/QC and are accessible on LTRMP’s website (http://www.umesc.usgs.gov/aquatic
/bathymetry.html) and by contacting Jim Rogala.
A-Team Report
Kirk Hansen reported that the
A-Team met on April 27, 2011 to discuss the draft report assessing the
indicators used in the 2008 Status and Trends Report and the LTRMP research
frameworks. Hansen said the meeting also
included five presentations on various LTRMP research efforts. He said the 2010 field station products list
is nearing completion.
LTRMP Product Highlight: Modeling Big River Dynamics
Barry Johnson described the
development and potential applications of two-dimensional pool-scale
hydrodynamic models of ecological and hydraulic processes. He said the hydrodynamic models simulate
water movement within the floodplain as discharge changes and determine the
distribution and abundance of habitat features.
These models can be used to plan and evaluate restoration efforts.
Johnson
said the Pool 8 Hydrodynamic Model was designed to 1) develop a two-dimensional
pool-scale model of flow in the channels and floodplain, 2) simulate a range of
flow conditions and resulting habitat features, 3) relate habitat information
to biota and water chemistry, and 4) use model output to inform an ecological
response model. Specifically, the
modeling was aimed to answer how the dynamics of flow, physical factors, and
habitat features over space and time affect ecology.
Johnson also provided an
example of model output for Pool 5, where the model provided useful insights
regarding phytoplankton and macrophyte distributions. Johnson explained that the models can inform a
range of restoration work on the UMR, including designing islands and drawdowns;
modifying flow distributions; estimating future changes in discharge dynamics;
and comparing habitats, biota, and management actions within and between pools
and reaches. Johnson said future model
development will focus on adding wind fetch, aquatic vegetation as a hydraulic
component and nutrient processor, and a transition of land cover types. Work will continue on incorporating the
Joint Venture Research
Barb Pardo joined by
teleconference to overview the USFWS’s
Pardo explained that, in
2007, the UMR and Great Lakes Region’s JV team used national bird conservation
plans to develop conservation strategies for each major bird group in the
region, outlining their specific population and habitat objectives. For example, from the Partners In Flight
North American Landbird Conservation Plan, the JV team created the UMR and
Great Lakes Region JV Landbird Habitat Conservation Strategy. The JV team then combined these strategies to
create the 2007 UMR and Great Lakes Region Implementation Plan, which defines population
and habitat objectives for all bird groups.
Pardo described JV’s research
priorities, including refining breeding habitat models, conducting behavioral
research, and evaluating non-breeding habitat.
She said JV’s monitoring priorities are to determine the status and
trends of bird populations and any causes of population changes, evaluate
conservation efforts, and inform conservation design. Pardo explained that the JV has a flex fund to
implement priority conservation projects.
To target habitat areas for restoring priority species, JV uses GIS to
identify the presence of a JV focal bird species, the habitat requirements for
those species, and how much of each habitat type is needed in certain areas to
meet population objectives. Pardo said
the JV’s bird strategies are available at:
http://www.uppermissgreatlakesjv.org/.
In response to a question
from Marv Hubbell, Pardo said the JV information can be used to determine bird
species and habitat conservation priorities along the Upper Mississippi and
Mike Jawson noted that USGS
serves on the UMR and Great Lakes Region’s JV management and science
teams. He said JV’s conservation
strategies and restoration tools are well-tested and have proven very
effective.
Habitat Rehabilitation and Enhancement Projects
District Reports
Brian Markert reported that
high water is delaying construction again this year in MVS, with work currently
suspended on Batchtown,
Jeff
DeZellar said MVP plans to finalize design on Capoli Slough and award a
construction contract for the project in FY 11.
DeZellar said MVP will increase its planning efforts on Harper’s
Jim Fischer, while
acknowledging the difficult obstacles associated with L&D 3 fish passage,
expressed his disappointment with the project’s schedule. He recalled that Corps staff had said a draft
DPR would be completed in March 2011.
DeZellar acknowledged Fischer’s concerns, but said the implementation
guidance for the WRDA 07 project review requirements was not available until
January 2010, after the PMP for L&D 3 fish passage was complete. This has created significant delays, since
MVP had to revise the PMP to include plans for an IEPR.
Marv Hubbell reported that
high water levels have delayed construction on Lake Odessa and Fox Island. He said MVR still plans to complete
construction on Lake Odessa and initiate construction on Fox Island this fiscal
year. Hubbell introduced Cathy Henry of
the USFWS. Henry said partners’ efforts
to complete
HREP Highlight:
Huron Island
Nate Richards described how
LTRMP data is being used in planning
In response to a question
from Bernie Schonhoff, Barry Johnson said the hydrodynamic models could also be
used in planning and evaluating projects such as Huron Island. However, Johnson said the approach that
Richards’ outlined should be effective and suggested that the Huron Island PDT
document its approach and results. Karen
Hagerty said
HREP-LTRMP Integration
Marv Hubbell recalled that
the EMP-CC agreed to explore the question of better integrating the HREP and
LTRMP components to enhance their overall effectiveness. He suggested that EMP partners take a
three-pronged approach, as follows:
·
All EMP partners
actively seek integration opportunities
·
USACE requires
the use of LTRMP data to help identify baseline conditions in DPRs
·
Partners adopt
component monitoring protocols for use in project monitoring, where
appropriate, including development and support of data storage and retrieval
Fischer expressed his support
for proceeding with Hubbell’s approach.
Other Business
The
upcoming quarterly meetings are as follows:
§
August 2011 —
o
UMRBA — August 16
o
EMP-CC — August
17 (a.m.)
o
Adaptive
Management Workshop — August 17 (p.m.)-August 18 (a.m.) (tentative)
§
November 2011 —
o
UMRBA — November
15
o
EMP-CC — November
16 (a.m.)
o
Possible IIA
meeting — November 16 (p.m.)
§
February 2012 — Quad Cities
o
UMRBA — February
28
o
EMP-CC — February
29 (a.m.)
o
Possible IIA
meeting — February 29 (p.m.)
The August 2011
NECC meeting is canceled due to lack of funding. Any future NECC and joint EMP-CC/NECC
meetings will be contingent on NESP funding.
If NESP receives FY 12 funding, the schedule above will likely be
revised to permit EMP-CC, NECC, and any joint sessions to be held on the same
day (i.e., November 16, 2011 and February 29, 2012). This would push the possible IIA meetings to
the following day.
Kevin Foerster and Charles
Barton recognized Bill Franz’s many contributions to EMP and the UMR.
With no further business, the
meeting adjourned at 4:30 p.m.
EMP-CC Attendance List
May 18, 2011
EMP-CC Members
|
Charles Barton |
U.S. Army Corps of Engineers, MVD |
|
Kevin Foerster |
|
|
Mike Jawson |
U.S. Geological Survey, UMESC |
|
Rick Mollahan |
Illinois Department of Natural Resources |
|
Pat Boddy |
Iowa Department of Natural Resources |
|
Walt Popp |
Minnesota Department of Natural Resources |
|
Janet Sternburg |
Missouri Department of Conservation |
|
Jim Fischer |
Wisconsin Department of Natural Resources |
|
Bill Franz |
U.S. Environmental Protection Agency, Region 5 |
Others In Attendance
|
Jeff DeZellar |
U.S. Army Corps of Engineers, MVP |
|
Marvin Hubbell |
U.S. Army Corps of Engineers, MVR |
|
Karen Hagerty |
U.S. Army Corps of Engineers, MVR |
|
Darron Niles |
U.S. Army Corps of Engineers, MVR |
|
Marshall Plumley |
U.S. Army Corps of Engineers, MVR |
|
Brian Markert |
U.S. Army Corps of Engineers, MVS |
|
Donovan Henry |
U.S. Army Corps of Engineers, MVS |
|
Bob Clevenstine |
U.S. Fish and Wildlife Service, UMR Refuges |
|
Jon Duyvejonck |
U.S. Fish and Wildlife Service, RIFO |
|
Amber Andress |
U.S. Fish and Wildlife Service, RIFO |
|
Cathy Henry |
|
|
Barb Pardo |
U.S. Fish and Wildlife Service, Region 3 (via phone) |
|
Barry Johnson |
U.S. Geological Survey, UMESC |
|
Steve Shults |
Illinois
Department of Natural Resources |
|
Olivia
Dorothy |
Illinois
Lieutenant Governor’s Office |
|
Bernie Schonhoff |
Iowa Department of Natural Resources |
|
Kirk Hansen |
Iowa Department of Natural Resources |
|
Robert Stout |
Missouri Department of Natural Resources |
|
Steve Sletten |
Atkins |
|
Brad Walker |
Izaak Walton League |
|
Tom Boland |
MACTEC |
|
Cecily Smith |
Prairie Rivers Network |
|
Don Powell |
SEH Inc. |
|
Barb Naramore |
Upper Mississippi River Basin Association |
|
Dave Hokanson |
Upper Mississippi River Basin Association |
|
Kirsten Mickelsen |
Upper Mississippi River Basin Association |